Practice
Insurance and Liens practice
The study guide gives this section 12 percent of the paper. 21 free questions here, 83 more in the paid bank.
All 21 free insurance and liens questions
-
A private job reaches completion. How late after that date may the owner still record an effective notice of completion?
Civil Code section 8182 permits an owner to record a notice of completion on the date of completion or within 15 days after it, so a notice recorded later does not comply and never shortens anyone's time to record a claim of lien.
-
Labor has stopped on a private job. How long must that stoppage run, and still be running, for a notice of cessation to be available?
Civil Code section 8188 requires a continuous cessation of labor for at least 30 days before the recording, and the cessation must still be running on the day the notice is recorded, so work that restarts on day 28 resets the count.
-
An owner has just recorded its notice of completion. How quickly must it deliver copies to the direct contractor and to claimants that gave preliminary notice?
Civil Code section 8190 gives the owner 10 days from the date the notice is filed for record to deliver copies to the direct contractor and to every claimant that served preliminary notice, because those are the people whose lien deadlines the notice shortens.
-
Before recording a claim of lien, giving a stop payment notice, or asserting a claim against a payment bond, a claimant must give preliminary notice to whom?
Civil Code section 8200 names three recipients, the owner or reputed owner, the direct contractor the claimant works under, and the construction lender if there is one, and compliance is a prerequisite to a valid lien claim or stop payment notice.
-
Which of the following is given a lien right by the Civil Code list of persons that provide work?
Civil Code section 8400 gives a lien right to any person that provides authorized work and names the direct contractor, subcontractor, material supplier, equipment lessor, laborer and design professional, so lessors and design professionals count alongside suppliers.
-
An owner properly records and serves a notice of completion. How much time does the direct contractor then get to record its claim of lien?
Civil Code section 8412(b) closes the direct contractor's window 60 days after the owner records a notice of completion or cessation, and that shortened date controls because the section runs to the earlier of it and 90 days after completion.
-
An owner disputes a recorded claim of lien and wants the property released by recording a lien release bond. What must that bond be?
Civil Code section 8424 requires a lien release bond of 125 percent of the claim of lien, or of the amount the claim allocates to the property being released, and it must be executed by an admitted surety insurer.
-
A claimant has recorded a valid claim of lien. Within what time must it commence an action to enforce that lien?
Civil Code section 8460 requires the enforcement action within 90 days after the claim of lien is recorded, and the claim expires and becomes unenforceable if the claimant lets that date pass.
-
Under the license law a current workers' compensation certificate must be on file at all times. That requirement is a condition precedent to what?
Section 7125 of the Business and Professions Code (B&P Code), in the version in force since January 1, 2025, makes the certificate a condition precedent at all five moments, so a licensee must have one on file at all times and not only when the license is first issued.
-
How may an employer other than the state secure the payment of workers' compensation in California?
Labor Code section 3700 gives an employer two lawful routes, insurance written by one or more insurers authorized to write compensation insurance in this state or a certificate of consent to self-insure from the Director of Industrial Relations, so paying claims as they come in is not securing compensation.
-
What does a payment bond on a construction project assure the property owner?
A payment bond stands behind the money owed for labor and materials, so it assures the owner that the people who supplied them will be paid and will not file liens against the property.
-
A contractor names the contractor's bond it must file in its advertising. What does the license law make of that reference?
Any reference to a bond the license law requires, made in advertising, soliciting or other presentments to the public, is itself a ground for suspension, so naming that bond in an advertisement puts the license at risk even though the bond is genuine.
-
A mechanics lien has priority over a mortgage, deed of trust or other encumbrance on the property that attached after which date?
Priority is measured from commencement of the work of improvement, so a lien outranks any mortgage, deed of trust or other encumbrance that attached after work started on the site, which is why a lender wants its deed of trust recorded before anything happens there.
-
Under a California workers' compensation policy, what is the insurer's liability to a proper claimant for compensation the employer owes?
Every compensation policy is conclusively presumed to contain the clauses this article requires, and one of them makes the insurer directly and primarily liable to any proper claimant, so the claimant does not have to chase the employer first.
-
How far ahead of the end of the policy period must a workers' compensation insurer give notice of nonrenewal?
The insurer must give notice of nonrenewal and its reasons at least 30 days but not more than 120 days before the policy period ends, so a notice sent five months out is as defective as one sent a week out.
-
What effect does the insured's bankruptcy have on a liability insurer's duty to pay damages for a loss during the policy?
A liability policy is read as providing that the insolvency or bankruptcy of the insured does not release the insurer from paying damages for injury or loss occurring during the life of the policy, so cover follows the loss rather than the contractor's finances.
-
A claimant backing a stop payment notice to a construction lender with a bond must post a bond of what amount?
A claimant may give a construction lender a stop payment notice accompanied by a bond equal to 125 percent of the claim, and that bond answers for the costs and damages the owner, direct contractor or lender suffers if the claimant loses.
-
A payment bond was recorded before the work of improvement was completed. When must an action on the bond be commenced?
Where a payment bond is recorded before the work of improvement is completed, the statute bars an action to enforce liability on the bond later than six months after completion, so a claimant that waits longer loses the bond claim.
-
What happens to a license when the licensee fails to maintain a sufficient bond required by the bonding article?
If a licensee fails to maintain a sufficient bond required by the article, the license is subject to suspension or revocation, so a lapsed bond puts the license status itself at risk rather than drawing a money penalty.
-
What penalty follows a failure to observe a workers' compensation stop order served on an employer?
Failing to observe a stop order is a misdemeanor punishable by imprisonment in the county jail not exceeding 60 days or a fine not exceeding $10,000, or both, so working through the order carries its own criminal penalty.
-
Whose bodily injury does commercial general liability insurance protect a contractor against liability for?
Commercial general liability insurance protects the insured contractor against liability to the public, employees excepted, for bodily injury, property damage or personal injury, because injury to an employee belongs to the workers' compensation line instead.
What this section covers
What a contractor has to carry, and what a contractor can do when a bill goes unpaid. A current workers compensation certificate is a condition of holding a license at all, and the lien and stop-payment remedies run on deadlines a closed-book exam is built to test.
The study guide lists these topics under it:
- Workers compensation insurance
- Business insurance
- Liens and other remedies
Topics and share from the Law and Business study guide, form 13E-LAW, rev. 03-2026. The guide adds that the percentages are approximate.